Lessons Learned reports are available via two different menu options in EcoSys Projects:
-
From Lessons Learned screen: To view the reports from the Lessons Learned screen, follow the procedure below.
-
Navigate to Contracts > Lessons Learned.
-
At the top of the screen, in the green parameter bar, click the Contract ellipsis to view all the contract details.
-
Click the Reports tab.
-
Click the Lessons Learned Register hyperlink.
-
Click the Contract ellipsis to select the required contract. By default, the last selected contract appears.
-
Click RUN to preview the report.
-
-
From Reports menu: To view the reports from the Reports menu, follow the procedure below.
-
Navigate to Reports > Contract Registers > Lessons Learned Register.
-
Click the Contract ellipsis to select the required contract. By default, the last selected contract appears.
-
Click RUN to preview the report.
-