The Installed Quantities Progress Method should be assigned in the upper panel and that value saved before adding Contract Installed Quantities data.

  1. Navigate to Progress > Contract Value of Work Done.

  2. At the top of the screen, in the green parameter bar, click the Contract and Contract Period ellipsis to select the required contract and period.

  3. Click Refresh for screen update.

  4. Click the Contact Progress tab.

  5. Click the Line ID hyperlink. The Contracts Progress Methods panel appears.

  6. In the Contracts Progress Methods panel, click the Installed Quantities tab.

  7. Click the Insert Row icon to add a weighted milestone.

  8. Select the Date.

  9. Type in the required Installed Quantity.

  10. Type in a Comment.

  11. Click SAVE. The UOM auto-populates in Installed Quantities tab. The values in the Weight % Complete and Preview % Complete in Contract Line Progress panel auto-populates.

  12. Click the Refresh icon in the far-right corner in the upper panel. The values in the Weight % Complete and Preview % Complete in Contract Line Progress panel auto-populates.