The Installed Quantities Progress Method should be assigned in the upper panel and that value saved before adding Contract Installed Quantities data.
-
Navigate to Progress > Contract Value of Work Done.
-
At the top of the screen, in the green parameter bar, click the Contract and Contract Period ellipsis to select the required contract and period.
-
Click Refresh for screen update.
-
Click the Contact Progress tab.
-
Click the Line ID hyperlink. The Contracts Progress Methods panel appears.
-
In the Contracts Progress Methods panel, click the Installed Quantities tab.
-
Click the Insert Row icon to add a weighted milestone.
-
Select the Date.
-
Type in the required Installed Quantity.
-
Type in a Comment.
-
Click SAVE. The UOM auto-populates in Installed Quantities tab. The values in the Weight % Complete and Preview % Complete in Contract Line Progress panel auto-populates.
-
Click the Refresh icon in the far-right corner in the upper panel. The values in the Weight % Complete and Preview % Complete in Contract Line Progress panel auto-populates.