Contract line items must be established prior to establishing a contract budget. New contract budget line Items cannot be added on this screen. Contract line Items must already be established using the Contracts > Contract Lines functionality.

For any contract line items with an Open status as indicated by yellow fill in the Start Date, End Date, Curve and UOM fields. The Start Date, End Date and Budget Curve must be established before the Original Budget Quantity, Original Budget Hours and Original Budget Cost can be time-phased. It is the user’s responsibility to ensure that the start date falls before the end date. If it does not, the time-phasing action will change the start date to the value set for the end date.