This procedure allows you to establish the contract change headers and also update some of their attributes for a selected contract using the Contract Change Register panel.

  1. Navigate to Changes > Contract Changes.

  2. At the top of the screen, in the green parameter bar, click the Contract ellipsis to select the required contract.

  3. If required, click REFRESH to update the screen.

  4. Click the Contract Change Register tab.

  5. Edit the Contract Change Name.

  6. Click the Type ellipsis to select the required contract change type.

    • Budget Change

    • Forecast Change

    • Scope Change

  7. Click SAVE..