Time-Phase Contract Budget Line Items - EcoSys - 4.11 - Help - Hexagon

EcoSys Contracts Help (4.11)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
4.11

Time-phasing can be accomplished manually or systematically. If a Contract Line has a "Manual" Curve Type, then the quantities, hours, and cost must be spread manually using the Time-Phasing tab. If a Contract Line does not have a "Manual" curve, then the Time-Phase Open Budget action is used to spread quantities, hours, and cost between the Contract Line start and end dates.

The time-phased results of spreading of quantities, hours, and cost via the Time-Phase Open Budget action may be viewed on the Time-Phasing tab. However, if the Curve Type is not "Manual", data cannot be updated.