Additional set-up is required for the Physical % Complete, Installed Quantities, and Weighted Milestones progress methods.
After set-up is complete updates to a percentage amount (Weighted Milestones and Physical % Complete progress methods) and/or actual quantities (Installed Quantities progress method) must be completed before VOWD is calculated.
Physical % Complete has to be updated each contract period before VOWD is calculated.