Before Physical % Complete can be updated, the Progress Method for the Contract Line must be set to Physical % Complete and the Contract Progress spreadsheet must be saved.
-
Navigate to Progress > Contract Value of Work Done.
-
At the top of the screen, in the green parameter bar, click the Contract and Contract Period ellipsis to select the required contract and period.
-
Click Refresh for screen update.
-
Click the Contract Progress tab.
-
Edit the Physical % Complete.
-
Click SAVE..