This procedure allows the resource manager to generate resource capacity.

  1. Navigate to Resource Management > Supply/Demand.

  2. Click the Year ellipsis and select the year for which you want to view resource capacity.

  3. (Optional) Click the Resource ellipsis and select the resource to filter.

  4. Click the Resource Capacity tab.

  5. Click the Calendar ellipsis and select the required calendar for the resource for which you want to generate resource capacity.

    If no calendar is selected, then EcoSys will select the Standard calendar by default.

  6. Click FTE/HT ellipsis and select if the employee works Full Time or Half Time.

  7. Type in the Resource Quantity.

  8. Click the Save icon. The fields Generate Capacity Link and Capacity auto-populate.

  9. Click the Generate Capacity hyperlink.

    EcoSys generates hours for the selected year against the resource based on the calendar. Also, it generates holiday transactions for the selected calendar.

    To view the allocated weekly hours for a particular resource, click the Capacity hyperlink against the resource.