This procedure allows the project manager to submit resource request for a project either individually or a group of resources at a time for a particular project.

Submit Resource Request Individually

This procedure allows you to submit resource request individually.

  1. In the Project Utilization panel, click the Staging Utilization hyperlink against the project for which you want to request resource.

  2. In the Resource Utilization Staging panel, click the Submit hyperlink against the required resource line item.

Submit Resource Request as a Group

This procedure allows you to submit resource request as a group.

  1. Click the Actions list and select Submit Project Requests.

  2. Click the Project ellipsis and select the project for which you want to request resource.

  3. Click RUN and then OK.

    All the Staging Utilization requests for the selected project are moved to Submitted state.