Project Schedule Admin screen allows the EcoSys administrator to define calendars which include the time-zone, start time, duration, working days, and non-working days in the Schedule Calendars panel.

You can also override the availability details on a particular date in a calendar. The calendar overrides are defined in the Schedule Calendar Overrides panel.