This process allows you to map the cost objects in the Approved Quantity Budget Items panel to a Plant Breakdown Structure or vice versa. Mapping transactions are created in the S3D Mapping Rules panel.
-
Click the Map to PBS tab.
-
Click the Project ellipsis and select the required project for which you want to map its cost objects to a PBS.
-
In the Approved Quantity Budget Items panel, click the Link hyperlink against the cost object which you want to map to the PBS.
-
In the Plant Breakdown Structure panel, click the Link hyperlink against the PBS item to which you want to map the cost object.
A transaction is created in the S3D Mapping Rules panel.
-
Transaction row appears in red color if the external key is not provided for the transaction, indicating there is a duplicate mapping rule.
-
You can map multiple cost objects with the same PBS item and vice versa.
-