An existing change approver can be replaced with another resource.

  1. Ensure that the project manager has added the new approver to the project in the Project Setup screen (Project > Project SetupWorkflow tab).

  2. Navigate to Admin > Projects Admin > Working Forecast Transactions.

  3. Click the Working Forecast Transactions tab.

  4. At the top of the screen, in the tool bar, click the Project and Version ellipsis to select the required project and Logs.

  5. Click the Refresh button.

  6. Click the filter icon. A text box appears.

  7. Type the Change Path ID to filter the working forecast transactions.

    The Change Path ID consists of the concatenation of the project number, the system hierarchy delimiter, and the change number. For example: PRJ-000130.CHG-000001.

  8. Click the Resource ID ellipsis to select the required approver ID.

  9. Click SAVE.