Estimate Tasks - EcoSys - 4.03 - Administration & Configuration - Hexagon

EcoSys Core and Projects Administration (4.03)

Language
English
Product
EcoSys
Search by Category
Administration & Configuration
EcoSys Standard Version
4.03

This procedure allows you to view, update, or delete Estimate Project related Tasks.

This screen should be used only by EcoSys configurators.

  1. Navigate to Admin > Estimates Admin > Tasks.

  2. At the top of the screen, in the tool bar, click the Project ellipsis and select the required Estimate Project.

  3. Update the Estimate Project components.

  4. Click SAVE.

  • When you click Delete hyperlink, a confirmation dialog is displayed. After confirming the deletion, the Task and its associated transactions will be deleted so that no items are orphaned.

  • When you click Delete Row(s) icon, only the task get deleted, not its transactions.

  • You can customize the view of the spreadsheet from the View settings option.