This procedure allows the administrator to assign the material line items to the crews. After the crew is assigned to a material line item, the Count value in the Unit Rate Material Library Creation panel increments by 1 for that material line item.

  1. Navigate to Admin > Estimates Admin > Enterprise Libraries > Unit Rate Library.

  2. Click the Unit Rate Library Creation tab. The Unit Rate Library Creation spreadsheet appears.
    The values in the Unit Rate Library Creation spreadsheet are entered by the administrator for the Unit Rate Library category in the Maintain Categories and Values screen (Enterprise Data > Maintain Categories and Values > Transaction Categories tab > Unit Rate Material Library category).

  3. In the Unit Rate Library Creation panel, click the Select hyperlink corresponding to the required material line item. All the available crews appear in the Crews panel.

  4. In the Crews panel, click the Add hyperlink. The Assign Crew for Unit Rate Installation dialog box appears.

  5. Click the Unit of Measure ellipsis to select the required unit of measure of the material.

    If you are adding the same material line item again to the same crew, select a different Unit of Measure.

  6. Type the Daily Output of the crew.

  7. Click the Run button. The material line item is added to the Unit Rate Library Details panel.

    In the Unit Rate Library Details panel, the Material Rate value updated for the Material Rate Table unit rate table in the Resource Rate Table screen appears.