In the Risk Settings, you can define the % Contingency Risk values and Risk ID format.

Define % Contingency Risk Values

To define the % Contingency Risk values for each level, follow the procedure below:

  1. In the Project Details panel, click the Project Settings tab.

  2. In the Risk Settings section, type the % Contingency Risk values for the following levels:

    • % Contingency Risk Low

    • % Contingency Risk Medium

    • % Contingency Risk High

  3. Click SAVE.

Define Risk ID Format

This procedure allows you to define a Risk ID format for the selected project. This includes prefixes, suffixes, and the ability to increment by any provided number. It is critical to establish the Digits (number of digits including leading zeros) as well as the Increment. If either of these numbers are missing, the ID will not be generated as expected. The hierarchy path delimiter (typically a period, or ".") must not be used in either the prefix or suffix.

To define the Risk ID format, follow the procedure below:

  1. In the Change Settings section, type the required Prefix.

    The prefix is added to the beginning of the Risk ID.

  2. (Optional) Type a digit in Next ID Base.

    The numbering of the Risk ID starts with this digit.

  3. Type a digit in Digits (Max 20).

    This is the length of the Risk ID.

  4. (Optional) Type a required Suffix.

    The Risk ID ends with this suffix.

  5. Type a digit in Increment.

    The Risk ID increments by this digit.

  6. Click SAVE. The Risk ID appears in the Risk ID Example (Max 40) box.