This process allows you to view the resource utilization details regionally.

  1. Navigate to Resource Management > Resource Management Dashboards.

  2. Click the ellipsis for each of the below fields and select the required values.

    • Year - Select the year to filter the resource availability and utilization

    • Start Week - Select the start week from which you want to view the resource availability and utilization

    • Project Week - Select the project week

    • End Week - Select the end week upto which you want to view the resource availability and utilization

  3. Click the Region tab.

  4. Click the ellipsis for each of the below fields and select the required values.

    • Region Pie - Select the regions in which you want to view the resource utilization in pie chart format

    • Chart A - Select the region in which you want to view the resource utilization indicator in the chart format

    • Chart B - Select the region in which you want to view the resource utilization indicator in the chart format

    • Chart C - Select the region in which you want to view the resource utilization indicator in the chart format

    • Chart D - Select the region in which you want to view the resource utilization indicator in the chart format

  5. If required, click REFRESH.

    The resource utilization details for the selected regions are displayed in the chart format.