When changes are made to cost rates, exchange rates, category or resource assignments, Recalculate Transaction Cost can be used to bring cost on transactions up-to-date in line with these changes.

This option will initiate a process to recalculate transaction costs in the following areas:

  • Actual

  • Working Forecast

  • Published Forecast

This will apply to all cost objects in the EcoSys database.

  1. Navigate to the menu Admin > Core Admin > Currencies and Rates > Recalculate Transaction Cost.

  2. A message will appear asking the user to verify that transaction costs should be recalculated.

  3. Click OK to start the process, otherwise choose Cancel.

    Depending on the volume of data, this process can be CPU-intensive and time consuming. Therefore, it is recommended that this is executed by administrators at times of minimal system usage when no other administrative processes are running.

    Lock the users out of the system. Issues may result from creation of new transactions during the process, as well as the users experiencing decreased performance.