This procedure allows you to setup a stage gate as a stage gate activation step. Once this stage gate is approved during the stage gate process, the project becomes active.

Set a project activation gate only by using the Set Project Activation Gate action.

If a stage gate activation gate is not set; by default, the last stage gate is considered as a stage gate activation step.

  1. Navigate to Admin > Portfolios Admin > Stage Gates Admin.

  2. Click the Actions list and select Set Project Activation Gate.

  3. Click the Stage Gate Process ellipsis to select the required stage gate process.

  4. Click the Stage Gate Activation Step ellipsis to select the required stage gate.

  5. (Optional) Type a Comment.

  6. Click RUN and then OK.