This procedure allows you to setup the weight for the selected prioritization factor. This weight is used in calculating a project’s prioritization score. In the Maintain Values panel, the first row’s ID is set to the value – Weight, and the Name is set to the <Prioritization Factor Name>, where the <Prioritization Factor Name> is the name of the selected prioritization factor.

  1. Type the Weight of the Prioritization Factor.

  2. (Optional) Type the Description for the selected prioritization factor.

  3. Click SAVE.

    The sum of weights of all the prioritization factors must equal 100. If not, a project’s prioritization score will not be calculated correctly.