The Project Analysis dashboard allows you to view the published status of the select project for the selected period. The project health and summary Key Performance Indicators (KPIs) updated and published for the selected period in Project Status Management screen appear. Charts display project cost information.

Follow the procedure below to view the portfolio status,

  1. Navigation to Portfolios > Project Analysis.

  2. At the top of the screen, in the green parameter bar, click the Project and Period ellipsis to select the required project and period.

  3. Click Refresh for screen update.

  4. The published project health and health description for the selected period can be viewed in the Project Health Product panel.

  5. The published KPI summary status for the selected period can be viewed in the Project Current Period KPI panel.

  6. In the S-Curve panel, the total current budget, current forecast, actuals, earned value of all projects in the project appear.

  7. In the Time-Phased Budget panel, current budget by cost account chart appears.

  8. The Project CPI Gauge chart displays the project’s CPI.