Portfolio Risk Impact for Detail Level Quantitative Analysis Method - EcoSys - 4.02 - Help - Hexagon PPM

EcoSys Portfolios Help (4.02)

Language
English
Product
EcoSys
Subproduct
Portfolio
Search by Category
Help
EcoSys Standard Version
4.02

This following procedure allows you to select the Projects under the selected Portfolio and calculate the risk impact for each using Risk Value Method.

  1. In the Risk Register panel, click the Risk ID hyperlink for which the Quantitative Analysis Method is Detail Level.

  2. Click the IMPACT tab.

  3. In the Portfolio Projects panel, select the required Project Name hyperlink.

    The Detail Level Portfolio Risk panel appears.

  4. (Optional) Click the Risk Type ellipsis to change the risk type.

    All Portfolio Risks must be created at the lowest level of the Portfolio Hierarchy.

  5. Type the Probability (percent).

  6. Click the Risk value Method ellipsis and select the required method to calculate the risk.

    According to the selected method, the mandatory fields to be filled in change.

  7. Type the Unmitigated Risk Value.

  8. Type the below values:

    1. Low (cost)

    2. Likely (cost)

    3. High (cost)

    4. Low (days)

    5. Likely (days)

    6. High (days)

      Enter the values for Low, High, and Likely (cost/days) according to the selected method.

  9. Type the percentages below:

    1. Cost Confidence (percent)

    2. Schedule Confidence (percent)

  10. Click SAVE.

  11. Click the Impact by Method hyperlink. The calculated risk impact values appear in the Risk Method Values dialog.