Follow the procedure below to generate the report with portfolio changes register data.
-
Navigate to Reports > Portfolio Cost Summary.
-
Click the Portfolio Cost Summary hyperlink. A dialog box appears with a title Project Portfolio Cost Summary.
-
Click the Portfolio ellipses to select the required portfolio. By default, the last selected portfolio appears.
-
Click the Run button. The preview of the report appears.