This following procedure allows you to calculate the impact of the Portfolio Risk using Risk Value Method.

  1. In the Risk Register panel, click the Risk ID hyperlink for which the Quantitative Analysis Method is Risk Level.

  2. Click the IMPACT tab. The existing action items appear.

  3. (Optional) Click the Risk Type ellipsis to change the risk type.

  4. Type the Probability (percent).

  5. Click the Risk value Method ellipsis and select the required method to calculate the risk.

    According to the selected method, the mandatory fields to be filled in change.

  6. Type the Unmitigated Risk Value.

  7. Type the below values:

    1. Low (cost)

    2. Likely (cost)

    3. High (cost)

    4. Low (days)

    5. Likely (days)

    6. High (days)

      Enter the values for Low, High, and Likely (cost/days) according to the selected method.

  8. Type the percentages below:

    1. Cost Confidence (percent)

    2. Schedule Confidence (percent)

  9. Click SAVE.

  10. Click the Impact by Method hyperlink. The calculated risk impact values appear in the Risk Method Values dialog.