This procedure allows you to add or remove a project from a portfolio.
Projects should be assigned to standalone portfolios or portfolios at the bottom of the portfolio hierarchy. They should not be added to parent portfolios.
-
Navigate to Portfolios > Assignments.
-
In Project Selection Register panel, do any of the following:
-
Click the Add hyperlink. This adds the selected project to the portfolio.
-
Click the Remove hyperlink. This removes the selected project from the portfolio.
-
-
If required, click the Refresh icon to update the screen to view the updated project data in the bar charts.