This section describes the prerequisites for configuring EcoSys with the P6 Adapter. You can use the table below as a pre-installation checklist before initiating the installation process. Complete the following steps before the scheduled installation.
|
# |
Prerequisite Steps |
|---|---|
|
1 |
EcoSys Installation This document assumes that you have configured EcoSys. If EcoSys is not installed, see the EcoSys Installation Guide. |
|
2 |
P6 Version Compatibility Refer to EcoSys Supported Platforms to validate that your P6 version is compatible with the software. |
|
3 |
Download, Install and Configure the P6 API This document assumes you have downloaded and installed the P6 API from Oracle onto the EcoSys application server. Configure the P6 API to use the P6 database that is to be configured with EcoSys integration. |
|
4 |
P6 Administration Settings EcoSys requires that you set Ignore Daylight Savings Time to False in the P6 Administrator Settings for the configuration that you are using with the API. The default location is Primavera P6 Configuration > Application. |
|
5 |
Passwords and Accounts Create a P6 user account (within P6) that is enabled for the API module. |
|
6 |
Schedule Staff Availability During the installation, a system administrator with Admin level access to the application server(s) will need to be available. |