This procedure allows you to close the open estimate projects. After the project is closed, you cannot edit its attributes.

  1. Click the Actions list and select Close Estimate Project.

    The Close Estimate Project dialog box appears.

  2. Click the Project ellipsis to select the required project.

  3. (Optional) Type the Comment.

  4. Click the Run button. The Close Estimate Project confirmation box appears.

  5. Click the OK button.

    To view the log entry, click the Project ID hyperlink and click the Log tab in the Project Details panel.