The time-phase settings defined (Start Date, End Date, or Curve) for each line item in the Original Budget screen (Budgets > Original Budget > Time-phasing tab) appear in the Forecast Settings tab.

Follow the procedure below to update the existing time-phasing settings.

  1. Navigate to Forecasts > Multi Project Forecast.

  2. Click the Time-Phasing Method ellipsis to select the required time-phasing method. The available time-phasing methods are listed below:

    • BCK - Back-Loaded

    • BEL – Bell Curve

    • FRN - Front-Loaded

    • LIN – Linear

  3. Select the required Start Date and End Date.

  4. Click the Save icon.