Smart Build produces a list of Bill Of Quantities (BOQ) which is used to map the quantities requested with unit rates within the estimation tool, so that EcoSys can produce costs.

This procedure allows you to create the cost for an estimate project.

  1. Navigate to Estimating > Smart Build BOQ Mapping.

  2. At the top of the screen, in the green parameter bar, click the Project ellipsis and select the required project.

  3. If required, click REFRESH to update the screen.

  4. In the BOQ Structure panel, click the ellipsis to select the potential project specific CS codes:

    For example, SB_CS01 Subcontractors - Select the type of subcontractor.

    The available CS codes differ from project to project based on the establishments in the Smart Build application.

  5. Click the Map hyperlink.

  6. In the Unit Rate Estimate panel, navigate to unit rates hierarchy and match the unit rates with the BOQ item by identifying the unique identifiers.

  7. Click the Add hyperlink.

    EcoSys creates all transactions and costs required to complete the task in the Estimate Transaction Details for CS Codes panel.