This procedure allows you to view or create a schedule WBS activity structure for a project.

  1. Click the Schedule Structure tab and then Schedule Structure Register tab.

  2. Right-click the rows list and select Insert Under. This creates a new row under the selected line item.

    Do not choose Insert or Insert Multiple options. If these options are used, the project structure will not be added as a part of the project unless the parent path ID is also specified.

    • The Insert Under option places the project structure below the selected line item.

    • If the Insert Row option is used, the project structure is placed at the same hierarchy as the selected line item.

  3. Type in a unique ID and Name for the schedule activity.

  4. Click the Type ellipsis and select the required project schedule structure type. The available project schedule structure types are listed below:

    • Control Account

    • Planning Package

    • Summary Level Planning Package

    • WBS

    • Work Package

  5. Click the Parent Path ID ellipsis and select the required parent.

    If you do not select parent path ID, EcoSys automatically selects the immediate parent available in the schedule activity structure after saving.

  6. Click the Cost Control Level ellipsis and select Yes.

  7. Click the ICMS Cost Categories and Groups ellipsis and select the required category.

  8. Click the Calendar ellipsis and select the required calendar.

  9. Click the Save icon.