Push Schedule Details to OB - EcoSys - 3.02 - Help - Hexagon PPM

EcoSys Projects Help (3.02)

Language
English
Product
EcoSys
Search by Category
Help
EcoSys Standard Version
3.02

This process will transfer the Resource Assignment transactions to the Original Budget. This includes time-phasing dates and curves.

  1. Click the Actions list and select Push Resource Assignments to OB.

  2. Click the Project ellipsis and select the project which you want to transfer its data to Original Budget.

  3. Click RUN and then OK.