The Resource Analysis Dashboard consists of three panels.

  • Resource Assignments

  • Expenses

  • Resource Hours Chart

The Resource Analysis Dashboard displays the resources assigned to all cost objects for a selected project. It also displays the cost details of resources for individual cost objects, transactions occurred, and the number of hours/days assigned to each resource.

Resource Assignments

In the Resource Assignments panel, the following resource attributes are displayed:

  • Object Path ID (SBS/WBS) - Displays the object path ID of the activity.

  • Activity Path ID - Displays the activity path ID.

  • Cost Account ID - Displays the cost account ID of the activity.

  • Resource ID - Displays the resource ID.

  • Description - Displays the description of the activity.

  • Curve - Displays the curve type.

  • Quantity - Displays the quantity of the resource.

  • UOM - Displays the units of measurement of the resource.

  • Hours - Displays the hours allocated for the resource.

  • Rate Source - Displays the source of rate.

  • Rate (Hrs) - Displays the rate of the resource per hour.

  • Cost - Displays the cost of the resource for the particular activity.

  • Currency - Displays the currency of the cost.

  • Cost in Object Currency - Displays the cost of the resource in US dollars for the particular activity.

    You can customize the view of the Resource Assignments panel and toggle different grouping options from the view settings.

Expenses

In the Expenses panel, the resource expenditure and transaction details are displayed.

The Transaction Date is the date on which the expenditure is recorded. For all other attributes description, see Resource Assignments.

You can customize the view of the Expenses panel and toggle different grouping options from the view settings.

Resource Hours Chart

In the Resource Hours Chart panel, the number of hours/days assigned to each resource are displayed in the bar format in cyan color.

The following other resource attributes are also displayed:

  • Resource ID - Displays the resource ID.

  • Start Date and End Date - Displays the working period of the resource. The same is represented in the bar format in the chart.

You can filter the resources and sort the display view of bar representation in different timescale. To do this, follow the below steps:

  1. Type the resource name in the Filter box to filter the resource.

  2. Click the Timescale Unit list and select the time unit.

    This spreads the chart bar on the selected time unit scale.

  3. Select the Show subscale check box.

    The selected subunit timescale is displayed below the timescale unit. This helps in identifying the utilization of resource in high-level.

  4. Click the Timescale Subunit list and select the time subunit.