This section helps you to view the prioritization factors along with their associated potential selection. Also, Prioritization Score, IRR (Internal Rate of Return), NPV (Net Present Value) values appear. These potential selections and the IRR as well as NPV values are selected for the project in the Portfolio Setup screen. Based on the potential selection, the prioritization score is calculated.

To view the prioritization score, click the Score tab in the Project Details panel.

To view the Score tab, change the Region setting from Hidden to an appropriate position in the Screen Layouts.

The fields listed below appear:

  • Growth - Growth of the project.

  • Cost Efficiency - Cost efficiency of the project.

  • Innovation - Extent of innovation in the project.

  • Risk Level - Level of risk in the project.

  • Resource Impact - The impact of the resources in the project.

  • Cost / Benefit - Cost or benefits in the project.

  • NPV – Net Present Value of the project.

  • IRR – Internal Rate of Return of the project.

  • Score – prioritization score of the project.

    • The formula used to calculate the Project Prioritization Score is:

      (Growth value selected*Growth Weight%) +

      (Cost Efficiency value selected*Cost Efficiency Weight%) +

      (Innovation value selected*Innovation Weight%) +

      (Risk Level value selected*Risk Level Weight%) +

      (Resource Impact value selected*Resource Impact Weight%) +

      (Cost/Benefit value selected*Cost /Benefit Weight%)

    • The values for the Growth weight, Cost Efficiency weight, Innovation weight, Risk Level weight, Resource Impact value weight, and Cost/Benefit value weight are set by the administrator.