This procedure allows you to create a new lesson learned with the entered name. For each lesson learned a Lesson ID is generated by the system. The lesson IDs are managed through the database. After creating a lesson learned, a log entry appears in the Log tab.

  1. Navigate to Projects > Project Lesson Learned.

  2. Click the Actions list and select Create New Lesson Learned.

  3. Click the Project ellipsis to select the required project. By default, the last selected project appears.

  4. Type in the Lesson Learned Name.

  5. Type in the Comment.

  6. Click RUN and then OK.