This process allows you to copy the scheduled WBS transactions to the forecast for the cost objects which are mapped.

Make sure Time-Phasing of Resource Assignments is done before running this action.

  1. Click the Actions list and select Push Resource Assignments to FCT.

  2. Click the Project ellipsis and select the project for which you want to push resource assignments to forecast.

  3. Type in the Comments.

  4. Click RUN and then OK.