Unmet Demand is the planned resource hours that are not utilized in any project.

This process allows you to view the Unmet Demand of resources.

  1. Navigate to Projects > Project Manager Dashboard.

  2. At the top of the screen, in the green parameter bar:

    1. Click the Project ellipsis and select the required project.

    2. Click the Project Period ellipsis and select the required project period.

  3. Click the Resource tab.

  4. In the Unmet Demand panel, click the Start Week ellipsis and select the required date from the same month that is selected in the Project Period.

    By default, the Start Week auto-populates with a date from the same month that is selected in the Project Period.

  5. Click the End Week ellipsis and select the required end week date up to which you want to find the unmet demand of resource hours.

  6. If required, click REFRESH to update the screen.