In this process, the budget headers are created first, then the budget details are created and manually associated with the appropriate budget name. After the budget details are created and time-phased (the latter only if the project was set up for time-phasing), the named budget is submitted for approval.

The budget process also differs if the project is set up for time-phasing. See Projects > Project Setup.