Only cost control objects assigned with the Time-Phase Forecast or Manual Details forecast methods can be edited in the Time-Phasing Manual Details panel.

The line items displayed represent a summary of individual line items with the same Cost Account, Resource, and UOM. This prevents the need to display and control potentially hundreds of line items that have been time-phased across a range of periods. 

  • To allow for maximum control of the working forecast, you may choose to first use a calculated forecast method, recalculate the working forecast, then use the Manual Details forecast method to discretely control working forecast line item totals or per period values.

  • If the Project Exchange Rate Table was not established in Project Setup, the system cannot calculate Cost in Project Currency.