This process creates a new forecast variance change. The Current Forecast and Working Forecast is compared to produce delta line items. Then, these line items are assigned to the new change, and are submitted for approval. Based upon the total change value, the change may be automatically approved and posted to the Current Forecast.

 Forecast Variance changes cannot be submitted for approval unless they pass all the validation checks.

Follow the procedure below to create the forecast variance changes.

  1. Click the Actions list and select Create Forecast Variance.

  2. Click the Project ellipsis and select the required project.

  3. Click the Forecast Variance ellipsis and select the required variance.

  4. Click RUN and then OK.