This procedure allows you to build an alternate project structure. New rows may be inserted either at or below the structure element currently selected. Fields can be populated by either typing and tabbing between fields, or directly selecting fields and entering desired data.

  1. Navigate to Projects > Alternate Structures.

  2. At the top of the screen, in the parameter bar, click the Project ellipsis to select the required project.

  3. At the top of the screen, in the parameter bar, click the Alternate Structure ellipsis to select the required alternate structure.

  4. Click Refresh for screen update.

  5. Click the Alternate Structure tab.

  6. Click the Rows icon and select Insert Under. This creates a new row under the selected line item.

    The Insert Under places the project structure below the selected line item. If the Insert Row icon is used, the project structure is placed at the same level as the selected line item. Hence it is recommended to use Insert Under.

  7. Type a unique ID.

  8. Type a required Name.

    (Optional) Click the Parent ID ellipsis to select the required line item.

  9. Click SAVE. The full Path ID will be displayed.