Project forecast reports are available via two different menu options in EcoSys Projects:

  • From Forecast screen: To view the reports from the Forecast screen, follow the procedure below.

    1. Navigate to Forecasts > Forecast.

    2. At the top of the screen, in the toolbar, click the Project Period ellipsis to select the required project period.

    3. Click the Reports tab.

    4. Click the hyperlink of the required report.

  • From Reports menu: To view the reports from the Reports menu, follow the procedure below.

    1. Navigate to Reports > Forecasts.

    2. Select the required report from the menu list. The report will be generated based on the last project selected.