To view the Actual Details by Commitment report, perform any of the following actions.
-
View the report in the Commitments screen:
-
Navigate to Budgets > Commitments.
-
Click the Reports tab.
-
Click the Actual Details by Commitment hyperlink. A dialog box appears with a title Actual Details by Commitment.
-
Click the Project ellipsis to select the required project. By default, the last selected project appears.
-
Click the Run button. The preview of the report appears.
-
-
View the report from the Reports menu:
-
Navigate to Reports > Commitments > Actual Details by Commitment.
-
Click the Project ellipsis to select the required project. By default, the last selected project appears.
-
Click the Run button. The preview of the report appears.
-