This procedure allows you to view the resources assigned and schedule details for the selected cost object in the project schedule.

  1. Click the BASELINE tab.

  2. In the Project Scheduler Set and View Baseline panel, select the cost object row for which you want to view the assigned resources.

  3. Click the SCHEDULE DETAILS - BASELINE tab.

    You can customize the view of the Schedule Details - Baseline spreadsheet from View Settings.