This process allows you to copy the scheduled WBS transactions to the forecast for the cost objects which are mapped.
Make sure Time-Phasing of Resource Assignments is done before running this action.
-
Click the Actions list and select Push Resource Assignments to FCT.
-
Click the Project ellipsis and select the project for which you want to push resource assignments to forecast.
-
Type the Comments.
-
Click RUN.