The Activity Weight must be established before earned value is calculated for any object with a Schedule Activity % Complete progress method.
The total weight of all activities established for an object item should equal 100. However, if it does not, the system can still calculate Schedule Activity % Complete assuming all activities have an established Weight and % Complete.
This procedure allows you to add or update the activity weight for an object item in the Schedule Activity % Complete panel.
-
Navigate to Progress > Earned Value.
-
Click the Earned Value tab.
-
In the Progress Method column, click the Schedule Activity % Complete hyperlink for an object. The Schedule Activity % Complete panel appears.
-
Edit or type in the required Activity Weight.
-
Click SAVE. The value in the Weighted Effective % Complete auto-populates.
Click the Delete Row(s) icon to delete the selected weighted milestone.