The Activity Weight must be established before earned value is calculated for any object with a Schedule Activity % Complete progress method.

The total weight of all activities established for an object item should equal 100. However, if it does not, the system can still calculate Schedule Activity % Complete assuming all activities have an established Weight and % Complete.

This procedure allows you to add or update the activity weight for an object item in the Schedule Activity % Complete panel.

  1. Navigate to Progress > Earned Value.

  2. Click the Earned Value tab.

  3. In the Progress Method column, click the Schedule Activity % Complete hyperlink for an object. The Schedule Activity % Complete panel appears.

  4. Edit or type in the required Activity Weight.

  5. Click SAVE. The value in the Weighted Effective % Complete auto-populates.

    Click the Delete Row(s) icon to delete the selected weighted milestone.