This process allows you to view the Productivity Hours parameters and related charts.

  1. Click the Productivity Hours tab. The productivity analysis costs appear in the Productivity Hours panel.

    The below listed details appear in the Productivity Hours panel:

    • Path ID - Displays the path ID of the object.

    • Name - Displays the name of the of the object.

    • BAC Hours - Displays the budget at completion hours of the object.

    • PV Hours - Displays the present value hours of the object.

    • % Complete - Displays the percentage complete of the object.

    • EV AC Cost - Displays the sum of estimated actuals and actuals hours of the object.

    • EV Hours - Displays the earned value hours of the object.

    • CPI Hours - Displays the cost performance index hours of the object.

    • SPI Hours - Displays the schedule performance index hours of the object.

    • TCPI Hours - Displays to complete performance index hours of the object.

    • TSPI Hours - Displays to complete schedule performance indicator hours of the object.

    • Cost Variance - Displays the cost variance of the object.

    • Schedule Variance - Displays the schedule variance of the object row.

    • IEAC1 Hours - Displays the independent estimate at completion of the object. The formula is BAC/CPI.

    • IEAC2 Hours - Displays the independent estimate at completion of the object. The formula used to calculate IEAC2 Cost is AC + (BAC – EV/ (CPI*.8) + (SPU*.2).

    • IEAC3 Hours - Displays the independent estimate at completion of the object. The formula is AC + (BAC-EV/CPI*SPI).

    • IEAC4 Hours - Displays the independent estimate at completion of the object. The formula is AC + (BAC-EV).

  2. To view the charts related to productivity hours,

    1. View the project performance hours chart in the Project Performance Chart panel. The BAC, EV AC, and EV values appear in a bar chart format.

    2. To view the performance variance chart or performance factor chart for specific objects, perform any of the following:

      • Click the CPI Cost hyperlink. The CPI and SPI costs specific to the object appear in a bar chart format.

      • Click the Cost Variance hyperlink. The cost variance and schedule variance specific to the object appear in a bar chart format.