This following procedure allows you to select the WBS level line item of the project and calculate the risk impact for it using Risk Value Method.

  1. In the Project Risk Register panel, click the Risk ID hyperlink for which the Quantitative Analysis Method is Detail Level.

  2. Click the IMPACT tab.

  3. In the Project Structure panel, select the required Project Name hyperlink.

    The Detail Level Project Risk Value panel appears.

  4. (Optional) Click the Risk Type ellipsis to change the risk type.

    The Detail Level Portfolio Risk panel appears.

  5. Type the Probability (percent).

  6. Click the Risk value Method ellipsis and select the required method to calculate the risk.

    According to the selected method, the mandatory fields to be filled in change.

  7. Type the below values:

    1. Low (cost)

    2. Likely (cost)

    3. High (cost)

    4. Low (days)

    5. Likely (days)

    6. High (days)

      Enter the values for Low, High, and Likely (cost/days) according to the selected method.

  8. Type the percentages below:

    1. Cost Confidence (percent)

    2. Schedule Confidence (percent)

  9. Click SAVE.

  10. Click the Impact by Method hyperlink. The calculated risk impact values appear in the Risk Method Values dialog.