This procedure allows you to delete all the Contingency Lump Sum Cost and Contingency % Cost for the Project. Also, it deletes the cost for which Include Cost is selected.

  1. In the Contingency Builder panel, click the Lump Sum/%Budget tab.

  2. Click the Actions list and select Clear Contingency Lump Sum and %.

  3. Click RUN.

    Project attribute is read-only.