To view the Project Budget Details by ABS report, perform any of the following actions.

  • View the report in the Original Budget screen:

    1. Navigate to Budgets > Original Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Details by ABS hyperlink. A dialog appears with the title Project Budget Details by ABS.

    4. Click the Project ellipsis and select the required project. By default, the last selected project appears.

    5. Click RUN. The preview of the report appears.

  • View the report in the Current Budget screen:

    1. Navigate to Budgets > Current Budget.

    2. Click the Reports tab.

    3. Click the Project Budget Details by ABS hyperlink. A dialog appears with the title Project Budget Details by ABS.

    4. Click the Project ellipsis and select the required project. By default, the last selected project appears.

    5. Click RUN. The preview of the report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Budgets > Project Budget Details by ABS.

    2. Click the Project ellipses and select the required project. By default, the last selected project appears.

    3. Click RUN. The preview of the report appears.