Analyze Project Changes - EcoSys - 4.11 - Help - Hexagon

EcoSys Projects Help (4.11)

Language
English
Product
EcoSys
Subproduct
Project
Search by Category
Help
EcoSys Standard Version
4.11

The Analysis tab provides advanced tools for the evaluation of time-phased change data both before and after change approval. You must select a Start Period and End Period to render the Change Impact Details panel. Optionally, you can also select a specific Change to filter view results.

Follow the procedure below to analyze the project changes.

  1. Navigate to Changes > Changes.

  2. Click the Analysis tab.

  3. If required, click REFRESH to update the screen.

  4. Click the Change ellipsis to select the required change. This displays selected change’s data in Change Impact Analysis panel.

    You can customize the view of the Change Impact Analysis panel from the view settings.

  5. In the Change Impact Details panel, click the Change Impact Chart tab.

  6. Click the Project ellipsis to select the required project.

  7. (Optional) Click the Change ellipsis to select the required change.

  8. Select a Start Period and an End Period of the project for which you want to view the change impact.

  9. Click RUN to update the chart.

  10. In the Change Impact Details panel, click the Change Analysis tab.

  11. (Optional) Click the Change ellipsis to select the required change.

  12. Select a Start Period and an End Period to display the range of cost columns for that particular period.

  13. If required, click REFRESH to update the screen.

    You can customize the view of the Change Impact Details panel from the view settings.