To view the Generate Project Performance Summary (Cost) report, perform any of the following actions.

  • View the report in the Earned Value screen:

    1. Navigate to Progress > Earned Value.

    2. Click the Reports tab.

    3. Click the Generate Project Performance Summary (Cost) report tab.

    4. Click the Project ellipsis and select the required project. By default, the last selected project appears.

    5. Click the Project Period ellipsis and select the required period. By default, the last selected period appears.

    6. Click the Run icon. The Project Performance Summary (Cost) report appears.

  • View the report from the Reports menu:

    1. Navigate to Reports > Earned Value > Project Performance Cost.

    2. Click the Project ellipses and select the required project. By default, the last selected project appears.

    3. Click the Project Period ellipsis and select the required period. By default, the last selected period appears.

    4. Click the Run icon. The Project Performance Summary (Cost) report appears.